Timeline

July 2009

Work begins

The scheme is underway. The first sites to see any work taking place are Marine Gate, Marine Drive and Ovingdean in Brighton, Portobello in Telscombe Cliffs and Friars Bay and Lower Hoddern Farm in Peacehaven.

July 2009

Fencing goes up

There is visible activity at Marine Gate and Friars Bay as fencing and reptile protection work is carried out ready for construction work to commence for digging of the shafts. Over in Marine Drive one lane of the dual carriageway has been closed in both directions (just past Roedean Café and the traffic island) to enable construction of a new pumping station.

August 2009

Portobello make-over begins

Southern Water's current wastewater treatment works at Portobello will be turned into a pumping station to take the wastewater on to the Peacehaven Wastewater Treatment Works. Construction teams will begin work at Portobello which when complete will have a grassed roof and has been designed not to affect sea views from Telscombe Tye.

September 2009

Major work begins at the main Peacehaven site

Following the environmental, archaeological and diversion of water and electricity works the main earth moving activities begin in preparation for the construction of the treatment works.

April 2010

Construction 'Springs' into action

One of the largest marine excavators in the world, the "Nordic Giant" will dig a trench in the sea bed to lay the pipe. When completed the 2.5km long sea outfall pipe at Friars Bay will recycle the treated wastewater out to sea.

April 2010

Tunnelling work begins at Ovingdean and Peacehaven

The latest proven tunnelling techniques and machinery, tunnel boring machines (TBM) will be used to construct the new sewer tunnel.

August 2010

Laying of the outfall pipe

The outfall pipe will be towed into position and lowered into the trench created by the "Nordic Giant".

September 2010

Work on major structures commences at the Peacehaven site

Work to excavate and construct the main underground tanks that treat the wastewater will begin shortly followed by construction of the main buildings.

Spring 2011

Tunnelling completes

Main tunnelling work will be complete and the TBM will be removed from the ground.

Summer 2011

Shafts complete

The work at Marine Gate, Marine Drive, Friars Bay and Roedean Way are all due to finish this spring

Autumn 2011

A world beater

The record breaking grass roof will start to be become visible at the Peacehaven treatment work site and the landmark structure at Marine Drive will also become visible.

Spring 2013

Cleaner Seas for East Sussex

The final pieces of work will be complete and the wastewater treatment works will be up and running. It means everyone can now enjoy cleaner seas in East Sussex.


Index     Site map     Legal     Privacy     Investors     Accessibility    
 
 
 

Site maintained by the Boxharry Content Management System