This page contains all the relevant fees and turnaround times relating to the applications for water and sewerage connections and requisitions from our infrastructure.

Most applications will require a fee which must be paid before the application can be processed. Payments can be made over the phone using Credit/Debit cards or by BACS.

Water application fees and estimated turnaround times
  Fee (inc VAT) VAT @ 20% Fee (exc VAT) Estimated turnaround time
Capacity Check See application form See application form See application form 15 or 25 working days*
S41 Water Main Requisition See application form See application form See application form See application form
S45 New Connection - On site connection See application form See application form See application form 10 working days
S45 New Connection - Other £336.00 £56.00 £280.00 20 working days
S185 Water Main Diversion £1740.00 £290.00 £1450.00 30 working days
Sewerage application fees and estimated turnaround times
  Fee (inc VAT) VAT @ 20% Fee (exc VAT) Estimated turnaround time
Capacity Check See application form See application form See application form 15 or 25 working days*
Build Over £948.00 £158.00 £790.00 20 working days
S98 Off-site Sewer Requisition £4672.80 £778.80 £3894.00 60 working days
S102 Sewers for Adoption £386.00 £64.33 £321.67 20 working days
S104 Sewers to be Offered for Adoption £618.00 £103.00 £515.00 20 working days
S106 Sewer Connection See application form See application form See application form 21 working days
Sewer Diversion - SW undertaking diversion work £2220.00  £370.00  £1850.00  30 working days 
Sewer Diversion - Developer undertaking diversion work £373.20  £62.20  £311.00  20 working days