I am developing a commercial property

Non-household customers can choose who provides their water retail services, such as billing. As a non-household customer, you’ll need to choose a retailer before requesting a connection from them.  A retailer will be allocated if you don’t choose one yourself. Temporary connections, in site welfare facilities, show homes or for temporary building supplies, all need a retailer. Visit Open Water to find out more on the changes and choosing a retailer. 

Building a commercial property

When you're building a commercial property, you’re usually going to need a new water connection to our water main, to have a water supply for your property and a connection to the public sewer to take the sewage away. If you’re building multiple commercial properties or a large commercial property that needs a large amount of water, especially water used in industrial processing or factories, you may need a water connection with a large diameter or a new water main. If you need a lot of water, we might need to make some changes to our network to be able to deliver this. To understand your best option and all required work, please send us a pre-development enquiry. We will be able to make the necessary checks and advise on the best option for your project.

Please note that we don’t provide internal meters for commercial properties, only external meters, so that we have easy access to the meter.

 

Building a block of flats

You’ll probably need a new connection to our water main for water when you’re building flats, as well as a connection to the public sewer to take the sewage away. This also applies to new blocks of flats/apartments or when converting an existing building into flats.

For less than five flats, you’ll need to lay individual connection services to each flat. If you’re building more than five, you’ll need a bulk supply, that you’ll separate internally. You’ll be able to choose between the boundary/bulk meter or individual meter.

Depending on how much water you’re going to use, you might need to apply for a new water main. If you’re building a large apartment complex, you’ll need to check the best way for you to get the water supply. If you need a lot of water, we might need to make some changes to our network to be able to deliver this. To understand your best option and all the required work, please complete a pre-development enquiry. We’ll be able to make the necessary checks and advise on the best option for your project. You have an option to provide your own meter carriers. Please refer to our guidelines for installing internal meters in new flats.

You’ll also need to apply for a sewer connection, if you’re disposing of wastewater into our sewer. Any sprinkler system for your commercial property can be requested using a standard water connection application.

Please check our pages Water Connection, Sewer Connection , New Water Main to understand if these applications are right for your project.

 

GetConnected portal

We have made it easier to connect with us. You can apply, make payments, track your project and talk to us using our GetConnected portal.

 

 

Here are the steps that we will take to get you connected

Don't worry, we’ll be in touch along the way to make sure everything goes smoothly.

 

Water connection
  1. You apply online and pay your application fee

    Fill in our online form and pay your application fee. We’ll review your application within 5 days.

  2. We provide your quote

    We carry out a site survey and produce the construction costs for your project within 28 days. Please refer to our water connection calculator to understand the approximate costs.

  3. You accept your quote and pay for the works

    You review the quote, accept and pay for the construction works, along with filling in our water regulations questionnaire.

  4. We complete the water regulations review

    You’ll need to fill in water fittings information which we will review within 10 days. For high-risk projects we may need to carry out an inspection.

  5. You lay your private supply pipe

    You may need to arrange a contractor to lay a private supply pipe from your property.

  6. You book your site inspection

    When your private supply pipe is laid, you’ll need to request an inspection before we complete your connection.

  7. We complete your water connection and install your meter

    Once we’ve completed our inspection, we then complete the water connection and install a meter within the next 21 days.

  8. You register your new billing account

    Your new water supply is now live. Register your new billing account for the water bills to be addressed to you.

Read more

 

New Water Main
  1. You apply online and pay your application fee

    You review the quote, accept and pay for the construction works, along with filling in our water regulations questionnaire.

  2. We provide your quote

    We carry out a site survey and produce your project quote within 28 days (42 days for complex projects).

  3. You accept, sign and pay for the works

    You review the quote, sign and pay for the works in order to proceed.

  4. We produce a design and arrange a meeting

    We produce a detailed design of your new water main and arrange a meeting to confirm the start date and agree the schedule for the work.

  5. You may need to provide a chlorination certificate

    We schedule our work and begin construction of the new water main. You may need to provide a chlorination certificate to be reviewed by our team (greater than 63 mm).

  6. We complete the new main connection

    We complete connection of the new main to our network within 90 days.

  7. You can apply for individual connections

    After we are connected, you can apply for individual service connections. See our Water Connection service.

Read more

 

Sewer Connection
  1. You apply online and pay your application fee

    Fill in our online form and pay your application fee. We’ll review your application within 5 days.

  2. We send you our approval

    We’ll do a technical review of your application and send you our decision or request further information on your proposal within 21 days.

  3. You carry out your work

    You’ll need to obtain necessary permits and arrange your contractor to connect into our sewer.

  4. You book your site inspection

    Request a site inspection to ensure that your connection has been carried out correctly.

  5. We send you a completion letter

    Once we are happy that your connection complies with our requirements, we’ll send you a completion letter.

 
 
 