We're investing in this area to reduce bursts and improve water supply. The area was recently left without water following a burst main and we want to help prevent this in future.

background

The new pipe has now been installed and all customers have been connected successfully.

Work is continuing in the High Street to complete water main renewals and is on schedule to complete by the end of March.

Final resurfacing work of roads is underway.

When things are happening

14 March - 18 March

Bettesworth Road junction to Smallbrooke Lane junction. This section of road will be closed to through-traffic

19 March - 21 March

Swanmore Road junction to Bettesworth Road junction. This section of road will be closed to through-traffic

28 March - 30 March

Swanmore Road from Ratcliffe Avenue junction to Partlands Avenue junction. This section of road will be closed to through-traffic 